Resources

Client Alerts, News Articles, Blog Posts, & Multimedia

Everything you need to know about BMD and the industry.

CLIENT ALERT: Construction Law Update: Communication is Key! And Other Lessons Learned From A Recent Public Project Court Decision

Client Alert

In a recent decision, the Ohio Court of Claims entered a $2.2 million judgment in favor of the general trades contractor, and against a public university, in connection with an on-campus renovation project. Mid American Construction, LLC v. Univ. of Akron, Ct. of Cl. No. 2016-00685JD, 2018-Ohio-4513.

Delivered as a “multi-prime” project, the university entered into separate contracts with a construction manager and an architect, in addition to separate contracts with the general trades, plumbing, HVAC, and electrical contractors. The project was delayed and the general trades contractor and university asserted breach of contract claims against one another, each arguing that the other party’s delays and failure to perform caused the other to suffer damages.

Following trial, Judge Crawford entered a decision finding that the university’s ongoing failure to pay for work, as well as problems with coordination and schedule, not only justified the contractor’s decision to walk-off the job, but also prevented the contractor from completing its work. Thus, the university was found liable to the general trades contractor in the amount of $2.2 million, while the university’s counterclaim was denied.

The Court’s detailed thirty-three (33) page decision offers many rules and reminders for public owners, contractors, construction managers, construction claims consultants, and damages experts alike:

1.  Communication is Key. In observing the risk inherent in all construction projects, Judge Crawford aptly noted: “[p]ublic construction contracts are vast documents containing thousands of construction and procedural details, all of which amount to legal promises, and some of which would be difficult to perform. Business at the construction site is performed by skilled and unskilled workers who seek to coordinate a schedule that is often developed at a laboratory away from the work site and without communication with those individuals putting one brick on top of another.”

The point is clear. Communication delivers results. The more communicative, transparent and effective the construction team functions, the better the results. In his opinion, Judge Crawford identified thirty (30) separate reasons for delays on construction projects, the majority of which arise in the pre-construction phase and can easily be avoided with more effective communication.

What are you doing to improve communication, both internally and with other project participants? 

2.  Control What You Can Control. This decision also serves as a reminder to project owners of the importance of selecting an appropriate project delivery method, taking steps to ensure that the design is adequately developed, considering input from all stakeholders, issuing payment in a timely manner, issuing timely approvals, delivering the site to the contractor in a timely manner, hiring qualified design and construction teams, and following the contract’s written notice requirements.

Likewise, it is incumbent on contractors to identify and provide notice of unrealistic schedules, errors in contract documents, apparent design errors, constructability concerns, and questions concerning scope. Contractors are also reminded that so long as they make an honest effort to perform their contracts, and do not willfully refuse to perform, they are entitled to some portion of the contract price so long as they achieve substantial completion.

3.  The Value (or Cost) of a Good (or Bad) Construction Manager. This decision is a cautionary tale for owners and construction managers alike as the university’s liability arose, in part, from the failings of its construction manager. If the owner chooses to implement the Construction Manager At-Risk project delivery method, it must carefully select a qualified construction manager. Equally important, construction managers must deliver value to the project and their owner clients by following contract requirements such as conducting partnering sessions with contractors, providing monthly progress reports, providing look-ahead schedules, maintaining accurate and current schedule updates, timely responding to RFI’s and executing CCDs, and appropriately coordinating among contractors.

4.  Credibility Matters. If a claim arises that escalates to litigation or arbitration, judges and arbitrators tend to believe and find credibility with witnesses who are not evasive when asked tough questions, maintain a patient and frank demeanor, and provide consistent answers supported by the project documents.

5.  Battle of the Experts. Along the same lines, if a claim arises that requires expert testimony, judges and arbitrators have a tendency to agree with experts who are well-qualified, thorough, maintain an objective demeanor and deliver objective explanations, and offer testimony that is not conclusory, but is based on support and factual detail.

6.  Liquidated Damages or Compensatory Damages, But Not Both. Liquidated damages are not available under Ohio law where the party seeking to impose them is found to have contributed to an unreasonable delay. However, even in instances where a court may find a liquidated damages clause enforceable, and the party seeking damages is not in breach, it is well-settled law in Ohio that a non-breaching party may not recover both compensatory and liquidated damages.

For additional information, please feel free to contact Attorney Justin Alaburda at Brennan Manna & Diamond. He can be reached at www.jmalburda@bmdllc.com, or (330) 253-9134. 


January 2025 Notice of Proposed Rulemaking Brings Notable Changes to HIPAA Security Rule

In January 2025, the U.S. Department of Health and Human Services proposed amendments to the HIPAA Security Rule, aiming to enhance cybersecurity for covered entities (CEs) and business associates (BAs). Key changes include mandatory compliance audits, workforce training, vulnerability scans, and risk assessments. Comments on the proposed rule are due by March 7, 2025.

Corporate Transparency Act Effective Again

The federal judiciary has issued multiple rulings on the enforceability of the Corporate Transparency Act (CTA), which took effect on January 1, 2024. Previously, enforcement was halted nationwide due to litigation in Smith v. U.S. Department of the Treasury. However, on February 18th, the court lifted the stay, reinstating the CTA’s reporting requirements. Non-exempt entities now have until March 21, 2025, to comply. Businesses should act promptly to avoid civil penalties of $591 per day and potential criminal liability.

Status Update: Physician Noncompete Agreements in Ohio

Noncompete agreements remain enforceable in Ohio if they meet specific legal requirements. While the AMA and FTC have challenged these restrictions, courts continue to uphold reasonable noncompete provisions for physicians. Recent cases, like MetroHealth System v. Khandelwal, highlight how courts may modify overly restrictive agreements to balance employer interests with patient care. With ongoing legal challenges to the FTC’s proposed ban, Ohio physicians should consult a healthcare attorney before signing or challenging a noncompete agreement.

Immigration Orders and Their Economic Impact on Small Business: Insights from Attorney and Former Immigration Judge Rob Ratliff

President Trump's recent executive orders, targeting immigration policies, could significantly impact small businesses in Ohio, particularly those owned by undocumented immigrants. With stricter visa vetting, halted refugee admissions, and potential deportations, these businesses face uncertainty, workforce disruption, and closures. Ohio's immigrant-owned businesses, especially in food services and transportation, contribute billions to the state economy, and any disruption could result in economic ripple effects.

Corporate Transparency Act Ruling from the U.S. Supreme Court

The U.S. Supreme Court recently ruled on the enforceability of the Corporate Transparency Act (CTA), lifting an injunction previously imposed by the Fifth Circuit. However, a separate nationwide injunction remains in effect, meaning businesses are still not required to comply with the CTA’s reporting requirements. FinCEN continues to accept voluntary reporting while enforcement remains paused.