CLIENT ALERT: Construction Law Update: Communication is Key! And Other Lessons Learned From A Recent Public Project Court Decision

Client Alert

In a recent decision, the Ohio Court of Claims entered a $2.2 million judgment in favor of the general trades contractor, and against a public university, in connection with an on-campus renovation project. Mid American Construction, LLC v. Univ. of Akron, Ct. of Cl. No. 2016-00685JD, 2018-Ohio-4513.

Delivered as a “multi-prime” project, the university entered into separate contracts with a construction manager and an architect, in addition to separate contracts with the general trades, plumbing, HVAC, and electrical contractors. The project was delayed and the general trades contractor and university asserted breach of contract claims against one another, each arguing that the other party’s delays and failure to perform caused the other to suffer damages.

Following trial, Judge Crawford entered a decision finding that the university’s ongoing failure to pay for work, as well as problems with coordination and schedule, not only justified the contractor’s decision to walk-off the job, but also prevented the contractor from completing its work. Thus, the university was found liable to the general trades contractor in the amount of $2.2 million, while the university’s counterclaim was denied.

The Court’s detailed thirty-three (33) page decision offers many rules and reminders for public owners, contractors, construction managers, construction claims consultants, and damages experts alike:

1.  Communication is Key. In observing the risk inherent in all construction projects, Judge Crawford aptly noted: “[p]ublic construction contracts are vast documents containing thousands of construction and procedural details, all of which amount to legal promises, and some of which would be difficult to perform. Business at the construction site is performed by skilled and unskilled workers who seek to coordinate a schedule that is often developed at a laboratory away from the work site and without communication with those individuals putting one brick on top of another.”

The point is clear. Communication delivers results. The more communicative, transparent and effective the construction team functions, the better the results. In his opinion, Judge Crawford identified thirty (30) separate reasons for delays on construction projects, the majority of which arise in the pre-construction phase and can easily be avoided with more effective communication.

What are you doing to improve communication, both internally and with other project participants? 

2.  Control What You Can Control. This decision also serves as a reminder to project owners of the importance of selecting an appropriate project delivery method, taking steps to ensure that the design is adequately developed, considering input from all stakeholders, issuing payment in a timely manner, issuing timely approvals, delivering the site to the contractor in a timely manner, hiring qualified design and construction teams, and following the contract’s written notice requirements.

Likewise, it is incumbent on contractors to identify and provide notice of unrealistic schedules, errors in contract documents, apparent design errors, constructability concerns, and questions concerning scope. Contractors are also reminded that so long as they make an honest effort to perform their contracts, and do not willfully refuse to perform, they are entitled to some portion of the contract price so long as they achieve substantial completion.

3.  The Value (or Cost) of a Good (or Bad) Construction Manager. This decision is a cautionary tale for owners and construction managers alike as the university’s liability arose, in part, from the failings of its construction manager. If the owner chooses to implement the Construction Manager At-Risk project delivery method, it must carefully select a qualified construction manager. Equally important, construction managers must deliver value to the project and their owner clients by following contract requirements such as conducting partnering sessions with contractors, providing monthly progress reports, providing look-ahead schedules, maintaining accurate and current schedule updates, timely responding to RFI’s and executing CCDs, and appropriately coordinating among contractors.

4.  Credibility Matters. If a claim arises that escalates to litigation or arbitration, judges and arbitrators tend to believe and find credibility with witnesses who are not evasive when asked tough questions, maintain a patient and frank demeanor, and provide consistent answers supported by the project documents.

5.  Battle of the Experts. Along the same lines, if a claim arises that requires expert testimony, judges and arbitrators have a tendency to agree with experts who are well-qualified, thorough, maintain an objective demeanor and deliver objective explanations, and offer testimony that is not conclusory, but is based on support and factual detail.

6.  Liquidated Damages or Compensatory Damages, But Not Both. Liquidated damages are not available under Ohio law where the party seeking to impose them is found to have contributed to an unreasonable delay. However, even in instances where a court may find a liquidated damages clause enforceable, and the party seeking damages is not in breach, it is well-settled law in Ohio that a non-breaching party may not recover both compensatory and liquidated damages.

For additional information, please feel free to contact Attorney Justin Alaburda at Brennan Manna & Diamond. He can be reached at www.jmalburda@bmdllc.com, or (330) 253-9134. 


Department of Education Proposes Redefinition of “Professional Degree,” Excluding Nursing and Limiting Graduate Loan Borrowing

The U.S. Department of Education has issued a Notice of Proposed Rulemaking that would redefine “professional degree” programs under the One Big Beautiful Bill Act. The proposal excludes nursing from the recognized list and would impose new borrowing limits for graduate students while eliminating the Grad PLUS program. Public comments are due by March 2, 2026.

First-of-Its-Kind Federal Ruling Finds Use of Consumer AI Tool May Destroy Attorney-Client Privilege

On February 10, 2026, Judge Jed Rakoff of the U.S. District Court for the Southern District of New York issued a first-of-its-kind ruling finding that documents generated by a criminal defendant using a consumer AI platform were not protected by attorney-client privilege after being shared with counsel. The court treated the AI tool as a third party, concluding that entering sensitive information into a publicly available platform may waive confidentiality. The ruling also suggests that the work product doctrine may not apply where AI-generated materials are created independently by a client rather than at counsel’s direction. The decision signals that parties should exercise caution when using consumer AI tools in connection with legal matters.

Your Golden Chance for H-1B Lottery Registration - March 2026

USCIS H-1B registration opens March 4–19, 2026. U.S.-based employees on valid nonimmigrant status are exempt from the $100,000 fee for change of status petitions. The new weighted lottery favors higher-skilled and higher-paid employees, improving odds for advanced degree holders and Wage Level 3 or 4 workers.

Invisible Algorithms: The Hidden Role of Artificial Intelligence in USCIS Immigration Processing

The Department of Homeland Security has confirmed that artificial intelligence and machine learning tools are now integrated into numerous operational functions within U.S. Citizenship and Immigration Services (USCIS). These tools are described as mechanisms to improve efficiency, reduce backlogs, and assist officers in managing an unprecedented volume of applications. DHS emphasizes that human adjudicators retain decision-making authority and that AI systems do not independently grant or deny immigration benefits. Find out how AI affects the U.S. immigration process.

OAAPN | Year In Review: 2026 Ohio Board of Nursing and Ohio Law Rules

Find out key changes to Ohio law and the Ohio Board of Nursing rules that have directly impacted APRN practice over the past year, including Psychiatric Inpatient Documents, Intimate Examinations, Signature Authority, Duties Related to Fetal Death, Retail IV Therapy Clinics, Release from Permanent Restrictions, Disciplinary Action, Course on Drugs and Prescriptive Authority, Overdose Reversal Drugs, Office Based Opioid Treatment, Withdrawal Management for Substance Use Disorder, Safe Haven Program, and more.