Ohio Senate Bill 49 – Ohio Expands Lien Rights for Design Professionals

Client Alert

Ohio Grants Long Awaited Lien Rights to Design Professionals

Effective September 30, 2021, Ohio granted limited lien rights to design professionals, including architects, landscape architects, engineers, and surveyors.

Ohio Governor Mike DeWine signed Senate Bill 49 into law on July 1, 2021. This new law established a statutory right to lien commercial real estate by Ohio design professionals who, until now, could not file a lien for non-payment of professional services.

Senator Vernon Sykes, a primary sponsor of Senate Bill 49, stated that the “legislation ensures that architects, engineers and other designers will get paid for their work, regardless of the outcome of their projects . . . It will support hardworking Ohioans by protecting the value of their labor . . ..”[1]

In What Circumstances Does a Design Professional Have Lien Rights?

Design professional lien rights only apply to private, commercial real estate projects. Single family residential projects and public projects are specifically excluded in Senate Bill 49. To be eligible for lien protection, the design professional must have a written contract with the commercial owner of the property interest that is signed by both parties. Lien protection is not available for the design professional’s employees, agents, or independent contractors. The lien amount is limited to the amount due to the design professional under the written contract. Therefore, it will be important to obtain signed, written authorization for additional and supplemental services, as well as base contract services.

How Do I Perfect My Lien?

To perfect the lien, the design professional must record a signed and notarized affidavit in the county where the commercial real estate is located. The affidavit must list:

  1. the name of the design professional;
  2. the name of the owner of interest in the commercial real estate;
  3. the name of the record owner of the commercial real estate if different than the owner of interest;
  4. a legal description of the commercial real estate sufficient to reference the instrument by which the record owner took title and permanent parcel number, if any;
  5. the parties to and date of the contract;
  6. the amount of the design professional’s claim under the contract; and
  7. a statement that the information is true and accurate to the knowledge of the design professional.

Within 30 days after recording the lien, the affidavit must be served upon all parties listed on the affidavit by a delivery method that provides proof of receipt. Although failure to serve will not invalidate the lien, it does allow the court to consider equitable remedies for such failure.

How Do I Enforce My Lien?

The design professional holding a perfected lien on commercial real estate may commence proceedings to enforce the lien by filing a complaint in the county where the commercial real estate is located naming all parties with an interest in the commercial real estate. The design professional’s lien is subordinate to any other valid liens, regardless of recordation date, and all previously recorded mortgages and liens. Because all other valid liens take priority over the design professional lien, collection on the lien may be challenging if there is limited equity possessed by the Owner. The design professional must commence proceedings to enforce the lien within two years, or within 60 days of receiving a Demand to Commence Suit. Otherwise, the lien is extinguished by operation of law.

Satisfying the Lien

Any person with an interest in commercial real estate that was subject to the lien or named in the affidavit may record an affidavit stating that the underlying lien was satisfied or that it was released by operation of law. The release of a lien does not affect the ability of the design professional to assert any other claim or appropriate action, including a claim for breach of contract. The lien may also be removed by filing a request to substitute financial security for the lien with the Court of Common Pleas in the county where the lien was recorded. The substitute security must be an amount equal to the design professional’s claim in a form such as an escrow account or surety bond held by the Clerk of Courts or other party determined adequate by the court. On approving such, the court shall direct the lien to be released.

Although not as robust as the lien rights of mechanic’s lien or judgment lien claimants, Senate Bill 49 provides design professionals with a relatively simple way to assert a lien against commercial real estate in order to compel payment of past due amounts for services rendered. It is expected that these lien rights would only be used as a last resort after all other reasonable efforts to secure payment have been exhausted.

For more information on design professional lien rights, please contact Construction Law Member Bob Hager at rahager@bmdllc.com or Attorney Abigail Peabody at aepeabody@bmdllc.com.

[1] https://ohiosenate.gov/senators/sykes/news/sykes-payment-assurance-legislation-for-design-professionals-signed-into-law


Medicaid Announces Next Generation of Managed Care Organizations

For the first time since 2005, the Ohio Department of Medicaid (“ODM”) made significant changes to the structure of the Medicaid program by finalizing the Medicaid Managed Care Procurement process. The Procurement process began in 2019 at the behest of Governor Mike DeWine who had a goal to make Medicaid managed care more focused on the health and well-being of individuals.

BMD Appellate Win Clarifies Waiver of Contractual Right to Arbitrate

Brennan, Manna & Diamond, LLC attorneys David M. Scott, Lucas K. Palmer, and Krista D. Warren prevailed before the United States Court of Appeals for the Sixth Circuit regarding if/when a party waives a contractual right to arbitrate. Borror Property Management, LLC v. Oro Karric North, LLC, No. 20-3146 (the “Decision”).

Relief for Ohio Under the Federal American Rescue Plan Act

On March 11, 2021, President Biden signed the American Rescue Plan Act (the “Act”) — a $1.9 trillion COVID-19 relief package — a significant portion of which will be directed to the State of Ohio to support economic recovery, as outlined below.

Cleveland Manufacturer Violated OFAC Sanctions By Allowing Shipments To Iran - Know Your Customer and Know Their Customer

UniControl, Inc., a Cleveland, Ohio manufacturer of process controls, airflow pressure switches, boiler controls and other instruments, agreed to pay the Office of Foreign Assets Control “OFAC,” the financial enforcement agency of the U.S. Treasury Department, $216,464 to settle its liabilities for violations of the Iran Sanctions Program. OFAC stated that “this enforcement action highlights the importance of identifying and assessing multiple warning signs that indicate a foreign trade partner may be re-exporting goods to a sanctioned jurisdiction.”

Ohio Breach of Contract Statute of Limitations Shortened to 6 Years

On March 16, 2021, Governor DeWine signed into law S.B. 13 which shortens Ohio’s statute of limitations for filing lawsuits based on breach of contract. A statute of limitation is the time period within which a party must file a lawsuit before its claim expires as a matter of law.