Ohio Supreme Court Liquidated Damages Analysis: Hindsight is not 2020!

News Article

In a case decided on February 24, 2016, the Ohio Supreme Court construed the enforceability of a liquidated damages provision in a public works construction contract. The Court held that when evaluating the enforceability of a liquidated damages provision in a construction contract, the court must conduct its analysis prospectively, based on the per diem amount of the liquidated damages at the time the contract is executed, and not retrospectively, based on the total amount of liquidated damages that ultimately accrue.

In reversing the Court of Appeals, the Ohio Supreme Court determined that the mere fact that the liquidated damages totaled $277,900 (calculated at $700 per day times 397 days late) did not result in a finding that the amount of liquidated damages was unreasonable where the base contract amount was $683,300. The flaw in the Court of Appeals reasoning was that it applied a retrospective analysis using hindsight. The long-standing test in Ohio requires the analysis to be considered at the time the parties entered into the contract.

The Ohio Supreme Court also held that “liquidated damages are not deemed a penalty simply because a project consists of new construction of an improvement that did not exist previously and no proof of damages is required to enforce liquidated damages pursuant to such a contract.”

This decision also includes an interesting overview of the Samson Sales tripartite test for distinguishing between an unenforceable penalty clause and a valid liquidated damages clause.

To read the Slip Op. No. 2016-Ohio-628, Boone Coleman Constr., Inc., v. Piketon, visit: http://www.supremecourt.ohio.gov/rod/docs/pdf/0/2016/2016-Ohio-628.pdf

Should you wish to consult with the author of this article, please feel free to contact Attorney Robert A. Hager at (330) 253–4925.


BMD’s Director of Marketing Jennifer Shankleton Elected as President of the LMA Midwest Region for 2023

Congratulations to Jennifer Shankleton, BMD’s Director of Marketing, on her recent election to President of the Legal Marketing Association (LMA) Midwest Region for 2023!  LMA is a premier professional association focused on empowering marketing, business development, and client service professionals.

Brennan Manna & Diamond Attorneys Featured in The Best Lawyers in America© and Ones to Watch™ 2023 Report

Brennan Manna & Diamond (BMD) is pleased to announce 17 BMD attorneys have been voted by their peers as The Best Lawyers in America© and Ones to Watch in America™.

Physician Non-Competition Agreements 2022

Contract provisions with restrictions on physicians practicing in the same area should they change employment have been around for decades. In Ohio, courts continue to state that while provisions are generally disfavored, non-competition provisions remain enforceable. Specifically, as to physician non-competes, the courts note that such agreements are further scrutinized regarding the adverse effect on the public interest to keep healthcare professionals in a community. Courts have continued in more cases than not to enforce restrictive covenants against physicians.

Immigration Attorney Talks Crisis in Ukraine (published by Community Legal Aid, 4/6/22)

Duriya Dhinojwala interview with Community Legal Aid

BMD Attorney Marlon Primes Appointed to the Georgetown Law Board of Visitors

BRENNAN, MANNA & DIAMOND attorney and former Assistant U.S. Attorney for the Northern District of Ohio, Marlon Primes, has been appointed to the Georgetown Law Board of Visitors.